In 2024, the Ministry of Energy of the Republic of Kazakhstan operated under its 5-year Development Plan for 2023–2027. Originally approved by Order No. 458 on December 30, 2022, the plan was updated four times over the following two years. These frequent updates reflect a flexible approach to strategic planning and the Ministry’s ability to adapt to changing circumstances.
At the start of 2024, the national budget allocated 161.9 billion tenge to the Ministry of Energy. However, after budget revisions, this amount was reduced to 154.5 billion tenge due to:
• Cost savings from procurement in gas transportation projects in the Almaty and Turkistan regions, as well as Astana;
• A shift of financing for a gas distribution network project in Taldykorgan to the National Fund;
• Delays in equipment delivery for the construction of the Astana CHP-3 power plant.
Despite the adjustments, total funding across all 11 budget programs of the Ministry reached 188.1 billion tenge, thanks to internal reallocations.
Financial discipline was exceptional:
Out of the planned 188,133,146.8 thousand tenge, 188,133,142.5 thousand tenge was executed — a 100% execution rate. Only 4.3 thousand tenge remained unspent, which is practically negligible.
In 2024, the Ministry implemented 11 major budget programsfocused on developing Kazakhstan’s fuel and energy sector. Key outcomes include:
• All 44 planned direct outcomes were fully achieved;
• All 6 final outcomes were also delivered as intended.
This demonstrates strong management and efficient use of public funds within the Ministry.