In 2024, the Ministry of Transport of the Republic of Kazakhstan operated under its official Development Plan for 2023–2027, which was updated several times throughout the year – most recently in December 2024. The ministry was primarily responsible for implementing major infrastructure projects, especially the construction and repair of national highways.
At the beginning of the year, the ministry was allocated ₸766.2 billion from the national budget. However, this amount was revised and increased during the year to ₸832.9 billion, with additional funds directed toward priority road infrastructure projects.
Some of the largest infrastructure investments included:
• Uzynagash–Otar project – construction funding;
• Kurty–Burylbaital section – completion and upgrading to four-lane traffic as part of the Karaganda–Almaty route;
• Balkhash–Burylbaital section – similar upgrades on the same corridor;
• Shakpak Baba tunnel (km 593–632) – payments to the contractor “Euraskon” for work already completed.
These routes are considered strategically important corridors for both domestic connectivity and international logistics.
Due to changes and updates, the number of budget programs increased to 24 in 2024. The total approved amount across all programs reached ₸882.1 billion, with ₸858.2 billion actually spent – a budget execution rate of 97.3%.
Funds left unused: ₸23.9 billion, including:
• ₸1.4 billion in savings;
• ₸22.5 billion unutilized.
In other words, about 1 out of every 27 tenge allocated to the ministry went unused – potentially a sign of planning gaps or delays in project execution.
Out of the 24 budget programs:
• 65 direct performance indicators were set; 64 were achieved, 1 missed.
• 22 final outcome indicators were set; 21 were achieved, 1 missed.
That means over 96% of all targets were met, suggesting strong overall performance. However, one program failed to deliver both its intermediate and final results, which deserves closer scrutiny.
Large-scale infrastructure projects aren’t just about asphalt and tunnels. They create jobs, support regional development, and lower logistics costs for businesses. The fact that the Ministry of Transport was able to spend most of its budget and meet most of its targets is a positive signal.
Still, the ₸22.5 billion left unspent represents missed opportunities, especially at a time when the national budget is tight.
Going forward, it’s crucial that budget adjustments and project plans are not only timely but also well-executed. Effective contractor oversight, quality control, and flexible planning are essential – not just to spend money, but to turn public investments into real benefits for citizens and the economy.